Change log for April 16, 2009
Errand day and a fussy baby made it difficult to do much today…
- Picked out a laminate countertop for the kids’ bath
- Picked out a manufactured granite countertop for the master bath
- Measured the cabinets for the countertops and found that the master bath counter may not work because of how the cabinet is laid out
- Bought the connector hose to hook up the water to the fridge
- Hooked up the fridge to the water and found that it didn’t work. We’ve also noticed that our water spigot outside the kitchen doesn’t work. However, since it used to work when the hot and cold water systems were linked together we think that the plumber who did our rough plumbing (no, not Matt) switched the hot and the cold lines. Whoops. By looking at the pictures I took before the drywall went up Matt thinks he has found the spot where the lines were probably switched. Matt is supposed to call the plumber to talk to him about it.
Some days feel like one step forward, two steps back…