Floor tile layed.
Floor tile sealed.
Floor tile grouted.
Bodies feel reeled.
Friday night Amber finished laying the floor tile while I did the telecom jack in the kitchen and worked on ceiling fan mount in the master bed room.
On Saturday I:
- set a recessed light in the downstairs hallway
- sealed the tile
- continued work on ceiling fan mount in master and started on mount in open area
- Cut metal for ceiling fans in master, open area and a bedroom, drill
In the afternoon on Saturday, Amber and I worked on pressure washing the house in preparation for painting. We put up some sample colors as we begin the long process of deciding what to use. I started doing some site pickup to prepare for the paining.
This morning I built the frame for the wall between the shower and toiled in the kids bath, finished the metal pieces for the ceiling fan, planned some additional conduit work needed for phone installation, continued outside pickup.
This afternoon Amber and I tested a new main paint color, pressure washed more and grouted the tile.
We’re very pleased with how the tile is looking – as Amber said earlier “It almost looks like we know what we’re doing!”. We’ve got some pics from the process so far and we’ll get them up at some point.