Brief Status Update

I feel like the month of January was mostly a time for catching our breath and figuring out what’s next.

The structure is totally up (walls and roof). Most internal framing is done. The roof material is on and most of the siding, trim and fascia are done. External doors are hung, windows are in and we’re totally dried in.

Next comes plumbing and electrical. We’ve been planning our electrical setup and the DWV lines that we’ll need to run and the implementation of these plans should start in earnest this month.