Change Log 04.23.09

Change log for Thursday, April 23rd, 2009

I drilled holes in 15 balusters to prep them for installation in the first railing section.

I thought about several other projects upstairs, but Nathan woke up early so I moved to the garden.  He is far too mobile to be trusted upstairs without a railing.  Emma and I weeded and I built a support structure for sugar snap peas, then Gregory and I planted pea seeds.  

I didn’t go to the house on Tuesday and Wednesday so there were no changes to report for those days.  Well, I did order the flooring for the bathrooms, pantry, mudroom and utility room on Tuesday so I suppose that counts for something!  That should be in sometime in the next two weeks or so.