Just had the inspection. I need to put in some additional GFI plugs in the kitchen.
We’re finaled and we can move in!
Just had the inspection. I need to put in some additional GFI plugs in the kitchen.
We’re finaled and we can move in!
The last 2 foot stretch of railing is complete upstairs. On Saturday I laid the oak flooring we needed (yes, it does take pretty much all day to lay about 16 square feet of recycled 2-1/4 oak flooring) and today I got the railing up then started work on finishing the kitchen light install and our temporary deck railing infill (it’ll make more sense with a picture).
While I was working on the floor on Saturday, Amber finished the laminate flooring in the boy’s room (yes, she laid half about 40 square feet in less time than it took me to do 16). Amber’s also been working on bundling some of our leftover oak flooring so that we can get the master cleaned and get laminate flooring down there.
The move-in list has been updated and it really does look like we’re getting close!
I installed the last toilet last night (in the master bath) so our plumbing is now officially done.
I’ve also planned our deck and done a material take-off for it. Amber’s working on planning the shelves for the pantry so we’ll order all that material tomorrow and have it delivered on Friday. I expect to get the deck built this weekend and may have time for exterior lights as well.
My goal for the 4th of July weekend was to get a working kitchen in the house. I started on Friday morning with backsplash material partly cut, counters still in full-size boards, range and dishwasher just occupying space (but out of boxes) and sink, faucet, garbage disposal and range hood still in boxes.
I’m happy to say that we now have a working kitchen.
We’ll post some pictures of the range, vent hood and overall kitchen some time in the next week.
I updated the
Move-In Checklist to reflect these changes.
Well, I haven’t been very good about getting change log posts up, have I. We’re still plugging away. We have someone working on the stairs and that will be done on Monday. Matt’s working on getting the kitchen together today and this weekend (after working on the oak flooring last weekend) and hopes to be done by the end of the weekend. I’ve been doing some more painting and cleaning, but most of the week has been taken up with kids’ activities. Tomorrow I hope to start installing the flooring we have for the bedrooms. The boys’ room is almost for that. I’m really looking forward to seeing that floor go down! If you look at the move-in list, you’ll see that we really are getting close… We might even be in our house in August. We shall see. I’m not feeling particularly excited, because it doesn’t really seem possible that we might be living there. It has just been too long of a process.
I’m not sure if anyone is still reading this, but anyways…
We have hot water now! Our propane tank is all hooked up and the hot water heater works. This was particularly welcome because I spent part of the afternoon pulling up poison oak with my bare hands. I was able to wash up with warm water rather than frigid, fresh from the well groundwater – a vast improvement. And yes, I know, this was not so bright of me, but it seemed like a good idea at the time. No rash so far, thankfully.
Other changes – I oiled the end of the counters with mineral oil and finished marking the knob locations for the kitchen cabinets.
First off, the railing. It isn’t quite finished, but we can at least let the kids upstairs without worrying so much!
Here’s our kitchen countertops
A shot of the end grain – they are finger jointed butcher block countertops, made by Perfect Plank in Chico, CA.
Here’s the mudroom and utility room with their new flooring
And the kids’ bath
The tub area of the kids’ bath
And the master bath (the floor is much more blue than it looks in this picture, btw)
Let me know if there’s anything else you’d like to see pictures of…
We’re really making some headway on our list these days! Over the past week we did a lot of cleaning up and we got ready for our flooring installation today. We also had the propane tank set today and our kitchen counters were delivered.
I installed plugs in Matt’s office and finally put a switch plate on the light switch in the storage area. I finished up the electrical outlets outside. I also finished painting the kids’ bath, fixed some drywall in there, and did some painting in the master bath. I started measuring the cabinets for knobs, but didn’t finish that yet. I spent a lot of time with the shop-vac and cleaned up a lot of dust and sawdust.
Matt installed the pedestal sink and faucet, nailed down the underlay in the upstairs bathroom, worked on the oak flooring upstairs, built a platform for the island future in the kitchen, and did a lot of picking up and putting tools and such away.
As you can see from the move-in checklist, we’re making a lot of progress! This week we should be getting our appliances, our propane hooked-up, and possibly five more doors. Once we have the appliances, Matt will be able to get those in place and then get the counters installed. Yay!
Change Log for Friday, June 5th to Monday, June 8th
I updated the Move-In Checklist and as you can see we’re slowly making progress. Emphasis on the slowly part!
Change Log for Friday, May 29th through Thursday, June 4th
I did a lot of cleaning up and organizing on Friday and through the weekend to prepare for having someone out to measure for our linoleum install. I also bought paint and I am working on painting the kids’ bath before the linoleum is laid down (currently scheduled for the 15th). I’ve put down a deposit and ordered the rest of our appliances (range, hood and dishwasher) and our kitchen countertop. I’ve ordered five more doors (pantry, utility door and pocket door, master bath, toilet area door for the kids’ bath). I’ve picked out the flooring for the bedrooms upstairs and for the open area and away room downstairs.
Over the weekend Matt worked on some of the window trim, installed the venting grates for the freezer, hung the door for the kids’ bath, and worked on the underlay for the kids’ bath.
We also had a plumber come out for the day on Tuesday and he installed all the shower hardware and the hot water heater. We’re supposed to get our propane tank installed next week, so we should have hot water soon.
FYI – I updated the Move-In List.